CAN DO - Humboldt Industrial Park WWTP, Hazleton, PA
WWTP Modifications Project (2005 - present)
Permitting and design for the project have been completed. Engineering support and construction
inspection is currently being provided for the Owner. The project included obtaining PA State
funding from the Pennsylvania Infrastructure Investment Authority (PENNVEST) for the plant upgrades
which include nutrient removal capabilities. Average daily flow for design processes was 1 MGD
with a peak hydraulic capacity of 2 MGD. The project construction cost is $5.2 million and
consists of the following:
- Influent pump station and head-works including, mechanical screening, grit settling and 1
million gallon equalization tank with course bubble aeration
- Anoxic tanks with zoned mixing
- Modifications of existing treatment tanks to accommodate the installation of fine bubble
aeration with DO control and clarifiers
- Effluent sand filters and chemical feed building.
Mechanical screen |
Screening, Grit Settling and Equalization Tank Pump Station
|
Pre-cast concrete equalization tank erection
|
Construction Site & Concrete Filter Structure
|
Head-work area and chemical feed building
|